Trail Paving Projects


Johnson & Sons Paving will begin work on five trail segments in Middleton starting August 11th with work on concrete ramps and detectable warning fields.  The existing path surface will be pulverized the week of August 14th with paving beginning on August 18th.  The project is anticipated to be completed by the end of August.  City crews have been doing prep work in some locations removing concrete and widening paths.  Please look for signage and use extra caution in these work areas, bikes should be walked thru construction zones.  The trails will be closed while Johnson & Sons is pulverizing the existing pavement. 

These areas include:
North Fork: Deming Way Underpass to Standard Imaging
Esser Pond: Deming Way to Terrace Ave
Park Street: Woodgate Rd to rail road tracks
Woodside Heights Park: Voss Parkway to Pond View Court
Stonefield Park: Clovernook Lane to tennis courts