PARMENTER ST. CLOSURE & DETOUR (8/3-8/7) As part of the Conservancy Bend development, the contractor will need to close northbound Parmenter St. near the roundabout to install water main beginning Monday, August 3. This will not affect southbound Parmenter St., and access will be maintained to all nearby businesses. The contractor will sign a detour route for northbound Parmenter St. to follow Franklin Ave., Park Lawn Pl., Park St. and Donna Dr. The contractor will replace the curb and provide a temporary asphalt patch on the street by the end of the week before opening the road to traffic again. In the event of significant rain delays, we may need to extend the duration of the temporary closure and detour.
|