Current Construction Projects

Overview

On this page are listed the major Public Works projects the City is undertaking in 2021. Under each heading there is a brief description of the project along with links to related documents and maps. The name and email of the City project manager for each respective project is shown immediately after the project name.

Among these are the City's annual projects for:

  • Street Reconstruction
  • Street Mill and Overlay
  • Street Chip Sealing
  • Sidewalk Repair

The first category above typically consists of one or two major street reconstruction projects. The second category provides new asphalt surfaces on several streets throughout the City. These projects are funded either by the Capital budget or by Tax Incremental Financing (TIF). In some cases, grants provide part of the funding.

The last two categories span multiple neighborhoods in any given year. Click the link below for the location of these projects for the current year.

Street & Sidewalk Projects Location Map 2021


Street Reconstruction

Aurora Street, Elmwood Avenue, Parmenter Street Reconstruction


Project 19-121    Project Manager: 
Shawn Ulsrud - Email
This project has been postponed until 2023.

Hubbard Avenue / Mayflower Drive


Project 20-122    Project Manager: Richard Weihert - Email
Project is substantially complete with some remaining restoration needed.  Given the time of the year the contractor is hopeful to get all the back filling completed very soon, however seed and mulch will need to be completed in the spring. Thank you all again for your patience during this long construction project. 

​Middleton Beach Road Reconstruction

Project 21-112    Project Manager: Shawn Ulsrud - Email
The scheduled start date for Middleton Beach Road reconstruction is spring of 2022 with completion date TBD.  The project includes pavement, water and forced main replacement as well as the addition of curb & gutter for better drainage. Driveway access will be maintained throughout the project during work hours to the greatest extent possible, but some daytime closures will be unavoidable. A detailed tentative schedule for the project has not yet been developed.  View plans here.

​Middleton Springs Drive Reconstruction

Project 21-118    Project Manager: Erik Sorensen - Email
The scheduled start date for street reconstruction of Middleton Springs Drive is Spring/Summer of 2022 with completion date TBD.  The project includes pavement reconstruction, geometry improvements, and drainage improvements.  Driveway access will be maintained throughout the project during work hours to the greatest extent possible, but some daytime closures will be unavoidable.  Business owners will be coordinated with prior to construction.  Some curb & gutter, sidewalk, and driveway aprons will be replaced.  A detailed tentative schedule for the project has not yet been developed. 

  • TBD: Public Information Meeting
  • TBD: Storm inlet repairs and Concrete replacement 
  • TBD: Manhole repairs  
  • TBD: Milling of old asphalt 
  • TBD: Undercut & grading of gravel road base 
  • TBD: Paving 
  • TBD: Cleanup/painting and buffer days for rain delays 

Pleasant View Road Reconstruction


Project: 15-106    Project Manager: Shawn Stauske - Email 
This project is scheduled to begin in the fall of 2022. It is a joint project between the City of Madison and the City of Middleton.

More information about the project can be found on the City of Madison website at the link below.

Pleasant View Road Reconstruction

Street Resurfacing (Mill & Overlay)  

Mill & Overlay is the resurfacing of a street by means of either a partial depth milling (removing only the top layer of asphalt) or full depth milling (removing the entire depth of asphalt without disturbing the underlying base course) then repaving with new asphalt. This type of work typically does not include underground utilities; it is meant to provide a new stable road surface at a lower cost than a full reconstruction.

The City intends each year to resurface several streets in various locations throughout the City. The locations for this year are shown on the project area map (see link above) identified in the legend as "Mill & Overlay."

Property owners will be notified prior to the start of the project. No daytime on-street parking will be allowed during the project, but access to driveways will be maintained whenever possible. This year's plans can be viewed at the link below.
2021 Mill & Overlay Plan Set


Shorecrest Street Resurfacing


Project: 22-104    Project Manager: Shawn Ulsrud - Email
The scheduled start date for street resurfacing of the Shorecrest Neighborhood is Spring of 2022 with completion by TBD. Driveway access will be maintained throughout the project each the evenings and during work hours when possible. Some curb & gutter (marked with pink paint) will be replaced in front of driveways, this concrete will need (5) five days to cure prior to driving over it with a vehicle. You will be given notice in person or as a notice on your front door 24 hours in advance. Once the project is complete, please be sure to water any newly seeded areas in front of your property to help promote the growth of the grass seed. Below is a tentative schedule for the project but can be subject to change due to weather or unforeseen construction issues.  

  • TBD: Storm inlet repairs and Concrete replacement  
  • TBD: Manhole repairs   
  • TBD: Milling of old asphalt  
  • TBD: Undercut & grading of gravel road base  
  • TBD: Paving  
  • TBD: Cleanup/painting and buffer days for rain delays  

Chip Sealing and Crack Filling

  
Project Manager: Shawn Ulsrud -Email

Project Update:

The chip sealing project is intended to prolong the life of existing pavements that are in reasonably good condition. Streets to be treated are selected by PASER ratings (asphalt condition) and to the extent possible, are grouped by neighborhood. One might view it as a "coat of paint" for the streets to prevent damage from water and UV light. The locations for this year are shown on the project area map (see link above), identified in the legend as "Crack Filling & Chip Sealing."

Prior to applying the chip seal material, the major cracks in the pavements are filled with a rubberized compound. This may be done either during the prior year or shortly before the chip sealing.

The next step is to apply a layer of emulsified asphalt to the road surface immediately followed by a layer of small aggregate chips. At this point, traffic on the road can resume. A few days later, after traffic has helped to set the aggregate, the road is swept and the project is complete.

No daytime on-street parking will be allowed during the project, but access to driveways will be maintained whenever possible.


Sidewalk Maintenance Program 


Project Manager: Tom Weber - Email

Each year the City inspects one-eighth of the City's neighborhoods to determine whether any sidewalks in those areas are deficient and in need of repair or replacement. See Street & Sidewalk Projects Location Map link located near the top of this page. More information can be found at the link below.

Sidewalk Maintenance Program


Pheasant Branch Restoration

Pheasant Branch Repair North of Century Avenue
Project 18-125k    Project Manager: Richard Weihert - Email

This project addresses the damage caused by the 2018 flooding, from Confluence Pond to Century Avenue.  Things included in this project are restoration, root wad installation, adding riprap.     
18-125k Bid Tab


Pheasant Branch Repair from Confluence Pond to Century Avenue
Project 18-125n    Project Manager: Richard Weihert - Email

This project addresses the damage caused by the 2018 flooding, from Confluence Pond to Century Avenue.  Things included in this project are restoration, realignment, root wad installation, adding riprap.   
18-125n Bid Tab